10-week program.1510 hours in labor
1485 tons of waste.
Value £142872.00
Appointed by D & R demolition.
The hotel underwent complete refurbishment and soft strip over 7 floors. Removal of asbestos insulation to pipe work.
Completed on budget.
Completed on program.